Schust Construction was awarded the contracts to install the following materials on this project:
- Centria Formawall Dimension Series Insulated Metal Panel
- Centria Formawall Graphix Series Insulated Metal Panels
- Centria Metalwrap Insulated Composite Backup Panel
- Centria BR5-36 EcoScreen Perforated Screenwall Panel
- Centria IW-10A Concealed Fastener Panel
- McElroy Metals Max-Rib Panel
- Construction Specialties Extruded Aluminum Soffit Louvers
- Stonewood Architectural Phenolic Fiberesin 8mm FR Panel
- John W. McDougall Co., Inc. Series 400 Rout & Return ACM Panel
- John W. McDougall Co., Inc. ACM Column Covers
Schust Construction was also awarded the contract to install 42,000 square feet waterproofing membrane under the green space. We utilized Carlisle 135 mil TPO Fleeceback membrane installed directly to the concrete deck.